Hy-Tec Quarry, Scotchy Pocket

Scotchy Pocket Quarry Road Reconstruction

Reconstruct 480m of bitumen haul road

  • True North Contracting successfully collaborated on a project to reopen a quarry within seven days, despite ongoing water flow on the road, demonstrating remarkable efficiency.

  • Efficient project planning led to early completion, with all necessary works, including bitumen road sealing, finished by day six, allowing the resumption of truck operations and customer sales by day seven.